BuildBlueprint requirements

Orders cover the selected hub region. Price history is regional, not station-specific.

Facts

FactValue
Max production limit200

Manufacturing

Time: 15m

Manufacturing materials
TypeQuantity
Sleeper Heat Nullifying Coil3
Tritanium6,944
Sleeper Data Crystals1
Sleeper Manuscripts2
Sleeper Foundation Block3
Manufacturing products
TypeQuantityProbability
Synthetic Hull Conversion Reinforced Bulkheads1
Manufacturing skills
SkillLevel
Industry5
Sleeper Technology1

Copying

Time: 12m

Research material

Time: 5m 15s

Research time

Time: 5m 15s

Industry cost

Industry cost calculator · materials after Material Efficiency and an estimated job installation cost

Formats